Area wise Quarters Summary

Till 25.05.2019


Repaired Status of Qtrs of Area
Action for repair of balance quarters

 

 

Area

Total No. of quarters (A)
Identified for repairs
Repairs completed till March 2019
(C)
Repairs done in the fortnight (D)
Total repairs in 2019-20
(E )
Cumulative
repair done till date
(F)= (C )+ (E )
Repair work started (Work order issued) No. of quarters (G)
Repair work yet to start (Work order issued) No. of quarters (H)
Tenders to be finalised for No. of Quarters (I)
Likely
date
of completion
Orient
4122
2622
1643
100
275
1918
704
0
0
Talcher
1405
1345
1001
10
65
1066
69
108
102
 
Jagannath
2140
1951
1845
4
106
1951
0
----
----
MCL HQ
655
613
414
414
199
0
0
Basundhra
468
468
468
468
----
----
----
----
IB Valley
1300
1299
1299
1299
0
0
0
Lakhanpur
1865
1765
1765
1765
----
----
----
----
CWS IB
102
101
101
101
0
----
----
----
Bharatpur
836
836
836
836
----
----
----
----
Hingula
787
745
745
745
0
0
----
Lingraj
899
899
899
899
0
0
----
CWS Talcher
294
294
294
294
----
----
----
----
NSCH
201
201
201
201
0
----
----
----
TOTAL
15074
13139
11511
114
446
11957
972
108
102
Oct'2019

 

 

Mahanadi Coalfields Limited