Area wise Quarters Summary (Till 10.09.2019)


Repaired Status of Qtrs of Area
Action for repair of balance quarters

 

 

Area

Total No. of quarters (A)
Identified for repairs
Repairs completed till March 2019
(C)
Repairs done in the fortnight (D)
Total repairs in 2019-20
(E )
Cumulative
repair done till date
(F)= (C )+ (E )
Repair work started (Work order issued) No. of quarters (G)
Repair work yet to start (Work order issued) No. of quarters (H)
Tenders to be finalised for No. of Quarters (I)
Orient 
4122
2622
1643
15
420
2063
559
0
0
Talcher
1405
1345
1001
0
134
1135
108
102
0
MCL HQ 
679
613
414
414
199
0
0
Jagannath 
2140
1951
1845
106
1951
0
----
----
Basundhra
468
468
468
468
----
----
----
IB Valley 
1300
1299
1299
1299
0
0
0
Lakhanpur
1865
1765
1765
1765
----
----
----
CWS IB
102
101
101
101
0
----
----
Bharatpur
836
836
836
836
----
----
----
Hingula
895
745
745
745
0
0
----
Lingraj
899
899
899
899
0
0
----
CWS Talcher
294
294
294
294
----
----
----
NSCH
201
201
201
201
0
----
----
Total  
15206
13139
11511
15
660
12171
866
102
0

Mahanadi Coalfields Limited