Bioprofile of Projects

 

Total Coal Mining Projects sanctioned till date in MCL are 53 (including 3 exhausted Projects). The rated Production Capacity of these sanctioned Projects was 285.61Mty, with a sanctioned Capital outlay of Rs.31734.03 Crs (including RCE). Out of total 53 Projects, 39 Projects are completed Projects and 14 Projects are On-going Projects. These 14 on-going projects have rated capacity of  201.83 Mty with capital investment of Rs.27463.11 Crs.

 


Project
Category

(Rs. Cr.)

No. of
Projects

Sanctioned

Sanctioned Capacity

(Mty)

Sanctioned
Capital

(Rs. Cr.)
Status
Exhausted
Completed
On-going

100 & above

21

232.40

30758.06

01

09

11

50 to 100

12

17.83

685.52

00

09

03

20 to 50

13

28.10

225.93

01

12

00

Below 20

07

7.28

64.52

01

06

00

Total

53

285.61

31734.03

3

36

14

 

1. Completed Projects-39 Nos.

Sl No. Name of the Project Total PR Cap (MTY) Total Sanctioned Capital(Rs. Cr.) Date of PR Approval

1.

Completed Projects till date- 39 Nos. (including 3 exhausted projects)

83.78

4270.92

Approved

 

 

2. On-Going Projects:-Total-14 Nos.

Sl No. Name of the Project Total PR Cap (MTY) Total Sanctioned Capital(Rs. Cr.) Date of PR Approval
A.) TALCHER COALFIELD

1

Ananta OC Expansion Ph-III

3.00 (Inc)

251.95#

31.08.2008

2

Balaram Expansion OCP

15.00

3504.21

04.08.2020

3

Bhubaneswari Expansion OCP

40.00

3145.45

25.08.2020

4

Gopalji-Kaniha OCP

30.00

8416.19

25.08.2020

5

Hingula-II OC Expansion Ph-III

7.00(Inc)

479.53

08.11.2008

6

Jagannath U/G  

0.67

80.75

15.10.2001

7

Nataraj U/G

0.64

92.11

30.01.2001

8

Talcher (West) U/G 

0.52

85.08

18.02.2002

9

Bharatpur Re-organisation OC

20.00

2838.87

12.11.2018

 

Sub total

116.83

18894.14

 
B.) IB VALLEY COALFIELD

10

Basundhara (W) Extn

7.00 *

**620.42

07.05.2014

11

Kulda Expn OCP

5.00(Inc)

**382.05#

25.06.2014

12

Siarmal OCP

40.00

**3756.36

29.05.2014

13

Garjanbahal OCP

10.00

**1375.38

03.05.2016

14

Integrated LKP-BEL-LIL OCP

30.00

2434.75

22.05.2018

Sub total

85.00

8568.97

 
TOTAL (Ongoing projects)

201.83

27463.11

 

GRAND TOTAL (Including capacity of exhausted mines)

285.61

31734.03

 

(*) No addition in capacity for extension project.

(**) As per approved RCE-cum-Completion Report and/or addl. capital sanctioned upto beyond target year.

(#)Including 10% of sanctioned capital within the DoP of CMD, MCL.

(^) Project approved “in-principle” with first year sanction only.

 

Future Projects: - 02 Nos.

Sl No. Name of the Projects Existing PR Capacity (MTY) Expansion PR Capacity (MTY) Remarks

1.

Subhadra OCP – (Utkal-A)

0.00

25.00

PR recommended by MCL Board on 30.10.2020. PR put up to Project Appraisal Committee (PAC) of CIL on 09.11.2020 and was considered in Empowered Sub-Committe (ESC) of CIL on 06.01.21.

2.

Kulda-Garjanbahal Expansion OCP

25.0

15.0

PR submitted by CMPDI to MCL on 23.12.20. Technical Sub-Committee of MCL will examine and recommend to MCL Board for approval