Bioprofile of Projects

 

Total Mining Projects sanctioned till date in MCL are 56 (including 3 exhausted Projects). The Rated Production Capacity of these sanctioned Projects is 277.61Mty, with a sanctioned Capital outlay of Rs.31635.55 Crs (Including RCE). Out of total 53 Projects, 38 Projects are completed Projects and 15 Projects are On-going Projects. These 15 On-going projects have a capacity of 163.83 MTY with a capital investment of Rs. 26757.97 Crs.


Project
Category

(Rs. Cr.)

No. of
Projects

Sanctioned

Sanctioned Capacity

(Mty)

Sanctioned
Capital

(Rs. Cr.)
Status
Exhausted
Completed
On-going

100 & above

24

224.40

31252.14

1

08

15

50 to 100

12

17.83

685.52

0

09

03

20 to 50

13

28.10

225.93

1

12

00

Below 20

07

7.28

64.52

1

06

00

Total

56

277.61

31635.55

3

35

18

 

1. Completed Projects-38 Nos.

Sl No. Name of the Project Total PR Cap (MTY) Total Sanctioned Capital(Rs. Cr.) Date of PR Approval

1.

Completed Projects till date- 38 Nos. (including 3 exhausted projects)

83.78

3719.39

Completed

 

 

2. On-Going Projects:-Total-15 Nos.

Sl No. Name of the Project Total PR Cap (MTY) Total Sanctioned Capital(Rs. Cr.) Date of PR Approval
A.) TALCHER COALFIELD

1

Ananta OCP Expn. Ph-III**

3.00

251.95

31.08.2008

2

Balaram Expn. OCP**

7.0

3504.21

04.08.2020

3

Bharatpur Re-organisation

20.00

2838.37

12.11.2018

4

Bhubaneswari Expn. OCP**

20.00

2674.96

25.08.2020

5

Hingula-II OCP Expn. Ph-III**

7.00

479.53

08.11.2008

6

Jagannath Re-organisation 

6.00 *

337.66

26.05.2014

7

Jagannath U/G 

0.67

80.75

15.10.2001

8

Gopalji-Kaniha Expn OCP**

20.00

7878.27

25.08.2020

9

Natraj U/G

0.64

92.11

30.01.2001

10

Talcher (W) U/G  

0.52

85.08

18.02.2002

 

Sub total

78.83

18222.89

 
B.) IB VALLEY COALFIELD

11

Basundhara (W) Extn

7.00 *

620.42

07.05.2014

12

Kulda Expn OCP

5.00

348.16

25.06.2014

13

Garjanbahal OCP

10.00

1375.38

03.05.2016

14

Integrated LKP-BEL-LIL OCP

30.00

2434.75

22.05.2018

15

Siarmal OCP

40.00

3756.36

29.05.2014

Sub total

85.00

8535.08

 
TOTAL (Ongoing projects)

163.83

26757.97

 

GRAND TOTAL (Including capacity of exhausted mines)

277.61

31635.55

 

(*) These are extensions of original Projects annexing additional areas. Hence, there will be no addition in Capacity.
(**) Ananta OCP Expn. Ph-III is 3 Mty Incremental Ongoing Project. Total PR capacity is 15 Mty.
Hingula-II OCP Expn. Ph-III is 7 Mty Incremental Ongoing Project. Total PR capacity is 15 Mty.
Balaram Expn. OCP is 7 Mty Incremental Ongoing Project. Total PR capacity is 15 Mty.
Bhubaneswari Expn. OCP is 20 Mty Incremental Ongoing Project. Total PR capacity is 40 Mty.
Gopalji-Kaniha Expn. OCP is 20 Mty Incremental Ongoing Project. Total PR capacity is 30 Mty.

 

Future Projects: - 06 Nos.

Sl No. Name of the Projects Existing PR Capacity (MTY) Expansion PR Capacity (MTY) Remarks

1.

Balaram Expn. OCP

8.0

15.0

Project Report approved by CIL Board on 05.08.2020.

2.

Bhubaneswari Expn. OCP

20.0

40.0

Project Report approved by CIL Board on 25.08.2020.

3.

Gopalji- Kaniha Expn. OCP

10.0

30.0

Project Report approved by CIL Board on 25.08.2020.

4.

Kulda - Garjanbahal Expn OCP

25.0

40.0

CMPDI has submitted the draft PR on 09.04.18. The PR was discussed by the Planning Committee of MCL on the 02.05.18. Updated Cost Estimate (UCE) is under preparation at CMPDIL.

5.

Subhadra OCP

0

25.0

Technical Sub-Committee has recommended the Project Report for approval in Outsourcing variant. MCL Board will consider the proposal in its forth coming Board of Director’s meeting.

6.

Balabhadra OCP

0

10.0

Project Report has been prepared and submitted by CMPDI. Technical Sub-Committee of MCL Board will examine and recommend to MCL Board for approval in October-2020.